From Sample to Bulk: A Typical OEM Timeline
New buyers often underestimate the time between approving a sample and receiving a container. Here is a realistic timeline for a custom heated jacket style, stage by stage.
Week 1-2: Brief and Quotation
Tech pack review, material sourcing and costing. A complete brief gets you a firm quotation and sampling plan within a week.
Week 2-3: Prototype
First article with your branding, heating layout and battery spec. Express shipping puts it in your hands for evaluation around day 12-15.
Week 3-5: Fit and Function Revisions
Most projects need one revision round — fit adjustments, heat level tuning or pocket placement. Each round takes 5-7 days.
Week 5-6: Pre-Production Sample and Deposit
The approved sample becomes the golden sample for bulk QC. Production slots are confirmed on receipt of the 30% deposit.
Week 6-12: Bulk Production
Material arrival (1-2 weeks), cutting and sewing (3-4 weeks), function testing and final inspection (1 week). Repeat styles compress to 4-5 weeks total.
Week 12-14: Shipping
Sea freight to US West Coast adds roughly 14-18 days door to door; air freight cuts this to 7-10 days at higher cost.